How long does it take to tile wet areas (bathroom and laundry)?

posted in: Uncategorized | 0

It can take anywhere between 8-14 working days for a small to medium sized domestic bathroom renovation. Factors that can impact the project timeline are as follows:

*Complexity of the job (hand cut mitres, intricate designs, amount of fixtures to be accounted for, etc)

*Type of tile being installed (stone tiling takes longer than ceramic or porcelain tiling and stone usually needs to be pre-sealed before installation and then a finale seal when grout is complete)

*Pattern of tile installation that take more time (Herringbone, Brick bond, Vertical Brick bond, Hexagon, Modular)

The Stages involved in a bathroom renovation include:

Stage 1 – Demolition

Stage 2 – Roughins (Plumber and Electricians are able to do any changes at this stage)

Stage 3 – Rendering and/or Plastering

Stage 3 – Waterproofing all wet areas. Usually entire bathroom as standard.

Stage 4 – Floor Tiling

Stage 5 – Wall tiling

Stage 6 – Grouting

Stage 7 – Silicone and Grout selanat